Case Study:


Calke Abbey Estate, Ticknall

Calke Abbey Estate, Ticknall

Construction of a Welcome Shelter

The construction of two welcome shelters , completed for the National Trust, Calke Abbey Estate, Ticknall , these works progressed whilst the estate was access by the employees and public

Further construction works included the cladding of toilet and changing rooms units including freestanding timber frame wall and roof canopy

Cladding of the catering unit including freestanding walls and roof canopy. .

Sector:

Education

Form of Contract:

JCT Minor Works with Contractor’s Design 2016 Edition

Client:

The National Trust

Duration:

Seven weeks

Project Manager:

Paul Hawood

Completion Date:

July 2019

Architect:

All Joyce Architedts Ltd.

Value:

£1.58m

Location:

Ticknall, Derbyshire