Case Study:


St Clare’s School, Mickleover, Derby – Refurbishment of Existing Building

St Clare’s School, Mickleover, Derby

Refurbishment of existing building

Bailey Construction successfully completed the refurbishment of an existing building at St Clare’s School, Mickleover, transforming the accommodation to provide modern, functional and high-quality learning spaces while preserving the character of the existing structure.

Delivering the project within a fully operational school required careful planning, close communication and meticulous coordination. Our team worked closely with the school to programme the works around the daily activities of pupils and staff, ensuring the school remained safe, accessible and fully functional throughout the construction period.

Maintaining the highest standards of health, safety and safeguarding was a key priority. Robust site management procedures, secure working areas and considerate construction practices ensured minimal disruption to teaching and learning, while protecting pupils, staff and visitors at all times.

The refurbishment involved upgrading the internal spaces to create a bright, modern environment, with high-quality finishes and improved facilities designed to meet the school’s current and future needs. Every aspect of the project was delivered with attention to detail, quality workmanship and a commitment to achieving the highest standards.

We are proud to have delivered another successful education project and would like to thank the school leadership, design team, consultants, subcontractors and the wider school community for their collaboration and support throughout the project. The result is a revitalised building that will continue to benefit students and staff for many years to come.

The site management was exceptional in forming relationships with the school and neighbours. Without the skill, diligence and management of the Bailey’s site staff, without doubt the project would have been more challenging” GNA Surveyors Ltd.

Sector:

Education

Form of Contract:

JCT Minor Works with Contractor’s Design 2016 Edition

Client:

Esteem Multi Academy Trust

Duration:

Fifty Four weeks

Project Manager:

Andrew Lucas

Completion Date:

September 2025

Architect:

CBP Architects

Value:

£5.3m

Location:

Mickleover,Derby